Glossary
The words of powered land.
40 terms used in buying, selling and developing powered land and data center sites, each defined in a sentence or two, with why it matters to a site.
Stages of a site
- Powered land
- Land under control, with power approved by the utility and zoning or use confirmed for a data center. Nothing is built yet.
- What changes hands is the land, the right to the power and the right to build. Acreage near a transmission line is not powered land until the utility has approved the capacity.
- Energy Buildalso energy infrastructure built
- A site with its energy infrastructure built: the utility's facilities, the substation, protection and commissioning. It may not be energized yet.
- The buyer skips the longest and least predictable part of the schedule, and pays for it.
- Powered shell
- A building, designed and permitted, with utility power delivered to it and nothing inside: no electrical distribution or cooling yet.
- The tenant fits out the inside to its own design.
- Fitted data centeralso turnkey data center
- A facility with the inside built out and commissioned: switchgear, UPS and backup power, power to the racks, and cooling. It is ready for servers.
- The fastest way to capacity, at the highest price per megawatt.
- Operating facility
- A running data center with its compute installed. What is sold is a business, with its customers and contracts.
- Diligence turns from construction risk to contracts and operations.
- Energization
- The moment utility power is first delivered to a site's facilities.
- It is the date a compute site is planned around. Until the utility's facilities are built, an energization date is a forecast.
- Greenfield and brownfield
- A greenfield site has never been developed. A brownfield site was used before, often by an industrial plant, and may keep that plant's grid connection, substation or water.
- An existing connection can shorten the path to power; an old use can bring cleanup and title questions.
Power and the utility
- Interconnection
- The physical and contractual connection of a generator or a large consumer of power to the grid.
- For a data center it decides how many megawatts arrive, when, and at whose cost.
- Large-load interconnection
- A request by a large consumer of power, such as a data center, to be served by a utility. Each utility and grid operator sets its own size threshold and process.
- The process usually runs from a request, through studies, to an agreement and then construction. It is the main driver of a site's schedule.
- Load studyalso system impact study
- The utility's study of whether the grid can serve a requested load at a place, and what would have to be built or upgraded to do it.
- Its result is the first real answer to how much power a site can have and how soon.
- Facilities study
- The engineering study that scopes, prices and schedules the specific equipment the utility must build to serve a load.
- It turns a study result into a cost and a date.
- Interconnection agreementalso service agreement, facilities extension agreement
- The contract between the customer and the utility that fixes the capacity, the schedule and who pays for what.
- A site's megawatts are firm only as far as this agreement says. Whether it can be assigned to a buyer is a first question in a sale.
- Tranche
- One block of a site's capacity, with its own size, date and approval status.
- A site described as 300 MW may be 50 MW now and the rest in later tranches that are still in study.
- Contribution in aid of constructionalso CIAC
- A payment by the customer toward the utility facilities built to serve it.
- It can be a large part of a site's cost and is usually due before construction starts.
- Point of interconnectionalso POI
- The place where the customer's electrical facilities meet the utility's.
- It sets what the customer builds and owns and what the utility does.
- Substation
- The facility that steps power down from transmission voltage to a voltage a site can use. Large loads usually need a dedicated one.
- Its transformers and switchgear are long-lead equipment and often set the schedule.
- Transmission and distribution voltage
- Transmission lines carry bulk power at high voltage, roughly 69 kV and above; distribution lines deliver it locally at lower voltage. Utilities draw the line between the two differently.
- Smaller loads can be served at distribution voltage. Large data centers typically connect at transmission voltage through their own substation.
- Transmission service provideralso TSP, distribution service provider, DSP
- In Texas, the utility that owns the transmission lines a site connects to. A distribution service provider owns the local lines.
- It is the party that studies the load and builds the connection, even where the customer buys its energy from someone else.
- Long-lead equipment
- Electrical equipment that takes many months to deliver once ordered: large power transformers, breakers and switchgear.
- Ordering it around the energization date, not after it, keeps a finished building from waiting on a transformer.
- Behind-the-meter generationalso BTM, on-site generation, co-location
- Generation on the customer's side of the utility meter that serves the load directly, with or without a grid connection alongside it.
- It can bring power sooner than the grid can, and brings fuel, permitting and reliability questions of its own.
- Firm and interruptible service
- Firm service is power the utility commits to deliver at all times. Interruptible, or non-firm, service can be reduced when the grid is under stress.
- Interruptible service can be approved sooner or priced lower. Whether a workload can live with it decides whether the site fits.
- Megawattalso MW
- A unit of power: one million watts. A site's capacity in megawatts is the most power it can draw at once; megawatt-hours measure energy used over time.
- Utility capacity is larger than the IT load it supports, because cooling and electrical losses draw power too.
Markets and price
- ISO and RTOalso independent system operator, regional transmission organization
- The organizations that run the grid and the wholesale power market across a region: ERCOT, PJM, MISO, SPP, CAISO, NYISO and ISO New England. Much of the Southeast and the West is run by utilities instead.
- The market a site sits in sets how power is priced and how a load gets connected.
- Interconnection queue
- The list of power plants and batteries that have asked to connect to the grid in a region.
- It shows where new supply is proposed and where developers are competing for the same lines. It does not show data center load requests.
- Locational marginal pricealso LMP
- The wholesale price of power at a specific point on the grid at a specific time.
- An indexed power contract follows it. Prices differ from place to place when lines are congested.
- Curtailmentalso demand response, flexible load
- Reducing a site's power use at the grid's request or in response to price.
- A load that can flex may get power sooner and cheaper. One that cannot needs firm service.
- Four coincident peakalso 4CP
- In ERCOT, the method that shares out transmission costs by each customer's demand during the system's peak in each of the four summer months.
- A load that can drop during those peaks can lower its transmission charges for the following year.
- Opportunity zone
- A census tract designated for tax-advantaged investment under federal law. A new map of zones takes effect on January 1, 2027.
- A site inside a zone may qualify an investor for tax benefits. Whether it does is a question for a tax adviser.
Land and the deal
- Land control
- The right to use or acquire a site: owned outright, held under an option, or under a signed contract or lease.
- A power approval is worth little without it, and options expire.
- Option agreement
- A contract giving the right, but not the obligation, to buy or lease land within a set period.
- It lets a developer hold a site while the power is studied, at a fraction of the purchase price.
- Letter of intentalso LOI
- A short document setting out the main terms two parties intend to agree, usually not binding except for confidentiality and exclusivity.
- It fixes price and structure before the cost of drafting a full contract.
- Purchase and sale agreementalso PSA
- The binding contract for the sale of a site, with its price, deposits, diligence period and closing conditions.
- Its deadlines run alongside the utility's, and the two have to fit.
- Non-disclosure agreementalso NDA, NCNDA
- A contract to keep shared information confidential. A non-circumvention clause adds a promise not to go around the party who made the introduction.
- A site's location, exact capacity and utility documents are shared only after it is signed.
- Data room
- The organized set of a site's documents shared with a buyer under NDA: utility studies and agreements, land documents, surveys, permits and reports.
- A buyer tests every claim about the megawatts against what is in it.
- Entitlementalso zoning
- The public approvals that allow a use on a piece of land: zoning, site plan and permits.
- A site with power but without the right to build a data center is not ready.
- Assignment
- The transfer of a contract's rights to another party.
- A power approval that cannot be assigned to the buyer may mean selling the company that holds it instead of the land.
- Asset sale and entity sale
- In an asset sale the land and the power position are sold directly. In an entity sale the company that holds them is sold.
- An entity sale leaves the utility agreements in the same name, so nothing has to be re-papered.
- Joint venturealso JV, co-development
- An arrangement in which the landowner or early developer stays in the project and shares in what is built.
- It trades a smaller payment now for a share of the later value.
Updated November 16, 2026. These describe how things generally work; a utility or grid operator's own rules decide any particular site. See also Insights, power data by state and the stages a site is sold at.