Power data

Power data by state

As of December 31, 2025, 8,413 active requests totaling 1,845 GW of generation and storage were waiting to connect to the U.S. grid. 445.2 GW of it (24%) has a signed interconnection agreement, and 1,257 GW proposes to be online by the end of 2028. The same data set records 22,833 withdrawn requests, 4,103 GW in all.

The opportunity zone map certified on November 5, 2026 takes effect January 1, 2027 with 6,576 tracts, 2,594 of them rural. By Belisari's comparison of the two maps, 3,601 are newly designated, 2,975 carry over, and 6,006 tracts on the 2018 map are not on the new one.

766.6 GWSolar551.8 GWBattery storage209.2 GWWind251.6 GWGas65.4 GWOther

Every state, by capacity in the queue

Open a state for its fuel mix, its counties with the most capacity waiting, who holds the queue, and its opportunity zones.

StateIn the queueRequestsAgreement signedOpportunity zones, 2027
Texas438.2 GW1,900125.9 GW608
California177.9 GW46081.9 GW620
Arizona106.9 GW27411.9 GW127
Oregon103.9 GW2804.7 GW58
Illinois73.7 GW41611.0 GW240
Michigan58.3 GW3007.5 GW215
Indiana57.1 GW28513.4 GW126
Nevada55.0 GW17320.9 GW49
Washington54.8 GW1823.5 GW99
Oklahoma52.5 GW23914.4 GW104
Colorado38.9 GW18711.1 GW91
Georgia38.3 GW16817.3 GW238
Louisiana37.6 GW1404.7 GW156
Arkansas35.4 GW1573.7 GW78
Kansas32.4 GW1389.2 GW53
Utah31.9 GW1414.1 GW37
Missouri29.7 GW1249.0 GW131
Virginia28.8 GW2717.3 GW153
Minnesota28.5 GW1531.3 GW73
New Mexico26.9 GW1437.3 GW65
Wisconsin26.8 GW1186.4 GW77
New York25.7 GW187—430
Iowa23.9 GW1232.8 GW44
Florida22.9 GW2302.9 GW342
North Carolina20.9 GW1793.6 GW204
South Carolina19.4 GW1932.4 GW113
Ohio18.4 GW1638.3 GW260
Kentucky17.1 GW1137.4 GW137
Wyoming16.2 GW735.2 GW20
Mississippi16.1 GW882.9 GW102
Nebraska15.8 GW805.4 GW28
New Jersey14.5 GW651.2 GW130
North Dakota14.5 GW622.4 GW25
Tennessee13.8 GW533.5 GW128
Idaho12.2 GW644.1 GW25
Pennsylvania11.4 GW2002.3 GW218
Montana11.3 GW451.2 GW25
South Dakota9.4 GW473.4 GW25
Alabama8.5 GW483.1 GW141
Massachusetts5.9 GW282.0 GW104
Maryland5.6 GW481.5 GW114
West Virginia5.2 GW341.3 GW52
Maine1.0 GW16850 MW25
Connecticut678 MW7648 MW61
Delaware505 MW850 MW25
Rhode Island278 MW2278 MW25
Vermont129 MW590 MW24
New Hampshire125 MW325 MW25
Alaska———25
District of Columbia———25
Hawaii———25

What the queue does and does not say

  • It is the supply side: power plants and batteries asking to connect. Data center and other load requests are not published by location.
  • Most projects that enter a queue are never built. A signed agreement is the best public sign that one will be.
  • Where the queue is deep, developers are competing for the same substations and lines, and studies take longer.

See it on the map

Belisari's power map draws the same data by county, with transmission lines, substations, power plants, gas pipelines and opportunity zones. It is free to use.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. A hybrid project's megawatts are split between its parts. “Agreement signed” means an executed interconnection agreement or a project in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones; the state counts cover the 50 states and the District of Columbia. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.