Iowa power data

As of December 31, 2025, Iowa had 123 active interconnection requests totaling 23.9 GW of proposed generation and storage, in 48 counties. Of that, 2.8 GW (12%) has a signed interconnection agreement, and 19.2 GW proposes to be online by the end of 2028. Iowa ranks number 23 among the states by capacity in the queue.

23.9 GW

In the queue

123

Active requests

2.8 GW

Agreement signed

19.2 GW

Proposed by 2028

What is waiting to connect in Iowa

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Wind7.3 GW30%
Gas6.4 GW27%
Solar5.2 GW22%
Battery storage3.3 GW14%
Other1.7 GW7%

Iowa counties with the most capacity in the queue

CountyCapacityRequests
Linn County3.6 GW14
Cerro Gordo County2.7 GW6
Marshall County1.6 GW6
Clinton County1.2 GW6
Franklin County1.1 GW7
Washington County1.1 GW3
Adair County791 MW3
Worth County775 MW5
Winnebago County720 MW3
Taylor County700 MW2

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
MISO23.7 GW120
SPP267 MW3

The same data set records 295 requests in Iowa that were withdrawn, 66.1 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Iowa

Iowa has 44 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 24 are newly designated and 20 carry over from the 2018 map; 21 are rural. 43 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.