Skip to content
Belisari
← Power data by state

Arizona power data

As of December 31, 2025, Arizona had 274 active interconnection requests totaling 106.9 GW of proposed generation and storage, in 12 counties. Of that, 11.9 GW (11%) has a signed interconnection agreement, and 80.3 GW proposes to be online by the end of 2028. Arizona ranks number 3 among the states by capacity in the queue.

106.9 GW

In the queue

274

Active requests

11.9 GW

Agreement signed

80.3 GW

Proposed by 2028

What is waiting to connect in Arizona

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Solar50.4 GW47%
Battery storage28.4 GW27%
Other18.9 GW18%
Wind5.2 GW5%
Gas3.9 GW4%

Arizona counties with the most capacity in the queue

CountyCapacityRequests
Maricopa County32.2 GW95
La Paz County14.7 GW10
Pinal County11.4 GW46
Navajo County11.2 GW25
Yuma County9.7 GW24
Mohave County7.9 GW22
Coconino County7.8 GW13
Pima County5.1 GW19
Apache County4.3 GW10
Yavapai County1.5 GW5

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
APS46.8 GW147
CAISO23.0 GW22
TEP11.0 GW36
SRP10.8 GW22
WAPA-DSW8.1 GW32

The same data set records 697 requests in Arizona that were withdrawn, 198.5 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Arizona

Arizona has 127 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 61 are newly designated and 66 carry over from the 2018 map; 40 are rural. 103 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.

Other states:TexasCaliforniaOregonIllinoisMichiganIndianaNevadaWashingtonAll states