Washington power data

As of December 31, 2025, Washington had 182 active interconnection requests totaling 54.8 GW of proposed generation and storage, in 27 counties. Of that, 3.5 GW (6%) has a signed interconnection agreement, and 35.1 GW proposes to be online by the end of 2028. Washington ranks number 9 among the states by capacity in the queue.

54.8 GW

In the queue

182

Active requests

3.5 GW

Agreement signed

35.1 GW

Proposed by 2028

What is waiting to connect in Washington

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Battery storage21.5 GW39%
Solar21.1 GW38%
Wind9.0 GW16%
Other2.2 GW4%
Gas1.1 GW2%

Washington counties with the most capacity in the queue

CountyCapacityRequests
Benton County16.3 GW27
Douglas County6.8 GW14
Grant County5.8 GW19
Yakima County5.1 GW13
Klickitat County4.7 GW15
Lincoln County1.9 GW9
Walla Walla County1.8 GW8
Garfield County1.5 GW4
Lewis County1.3 GW2
Columbia County1.2 GW5

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
BPA45.5 GW115
Avista4.3 GW34
PSE2.8 GW19
GrantPUD1.3 GW6
PacifiCorp858 MW7

The same data set records 503 requests in Washington that were withdrawn, 103.0 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Washington

Washington has 99 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 50 are newly designated and 49 carry over from the 2018 map; 36 are rural. 96 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.