Michigan power data

As of December 31, 2025, Michigan had 300 active interconnection requests totaling 58.3 GW of proposed generation and storage, in 57 counties. Of that, 7.5 GW (13%) has a signed interconnection agreement, and 40.6 GW proposes to be online by the end of 2028. Michigan ranks number 6 among the states by capacity in the queue.

58.3 GW

In the queue

300

Active requests

7.5 GW

Agreement signed

40.6 GW

Proposed by 2028

What is waiting to connect in Michigan

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Solar25.2 GW43%
Battery storage14.5 GW25%
Gas9.7 GW17%
Wind6.2 GW11%
Other2.6 GW5%

Michigan counties with the most capacity in the queue

CountyCapacityRequests
Monroe County5.0 GW10
Huron County3.9 GW17
Washtenaw County3.1 GW13
Branch County3.0 GW12
Van Buren County2.5 GW14
Livingston County2.4 GW7
Sanilac County2.4 GW11
Calhoun County2.3 GW12
Ottawa County2.2 GW7
Lenawee County2.1 GW12

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
MISO56.4 GW283
PJM1.8 GW17

The same data set records 390 requests in Michigan that were withdrawn, 70.5 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Michigan

Michigan has 215 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 114 are newly designated and 101 carry over from the 2018 map; 60 are rural. 185 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.