Indiana power data
As of December 31, 2025, Indiana had 285 active interconnection requests totaling 57.1 GW of proposed generation and storage, in 64 counties. Of that, 13.4 GW (23%) has a signed interconnection agreement, and 49.6 GW proposes to be online by the end of 2028. Indiana ranks number 7 among the states by capacity in the queue.
57.1 GW
In the queue
285
Active requests
13.4 GW
Agreement signed
49.6 GW
Proposed by 2028
What is waiting to connect in Indiana
The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.
| Fuel | Capacity | Share |
|---|---|---|
| Solar | 29.8 GW | 52% |
| Gas | 14.0 GW | 25% |
| Battery storage | 9.9 GW | 17% |
| Wind | 3.1 GW | 5% |
| Other | 260 MW | 0% |
Indiana counties with the most capacity in the queue
| County | Capacity | Requests |
|---|---|---|
| Sullivan County | 8.0 GW | 24 |
| Jasper County | 5.3 GW | 11 |
| Vermillion County | 4.6 GW | 11 |
| White County | 2.6 GW | 16 |
| Pulaski County | 2.6 GW | 10 |
| Porter County | 1.9 GW | 4 |
| Lake County | 1.6 GW | 8 |
| Vigo County | 1.5 GW | 8 |
| St. Joseph County | 1.5 GW | 7 |
| LaPorte County | 1.5 GW | 12 |
Who holds the queue
The grid operator or utility each request was filed with.
| Operator | Capacity | Requests |
|---|---|---|
| MISO | 41.3 GW | 180 |
| PJM | 15.8 GW | 105 |
The same data set records 578 requests in Indiana that were withdrawn, 114.3 GW in all. Most projects that enter a queue are never built.
Opportunity zones in Indiana
Indiana has 126 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 59 are newly designated and 67 carry over from the 2018 map; 42 are rural. 92 tracts on the 2018 map are not on the new one.
Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.
Reading this for a data center site
- The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
- A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
- Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.
3 sites in Indiana have been brought to Belisari's marketplace for powered land and data center sites.
Sources and method
Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.
Other states:TexasCaliforniaArizonaOregonIllinoisMichiganNevadaWashingtonAll states
