California power data

As of December 31, 2025, California had 460 active interconnection requests totaling 177.9 GW of proposed generation and storage, in 40 counties. Of that, 81.9 GW (46%) has a signed interconnection agreement, and 82.0 GW proposes to be online by the end of 2028. California ranks number 2 among the states by capacity in the queue.

177.9 GW

In the queue

460

Active requests

81.9 GW

Agreement signed

82.0 GW

Proposed by 2028

What is waiting to connect in California

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Battery storage100.1 GW56%
Solar64.1 GW36%
Wind8.1 GW5%
Other3.4 GW2%
Gas2.2 GW1%

California counties with the most capacity in the queue

CountyCapacityRequests
Kern County28.9 GW72
Fresno County22.9 GW43
Los Angeles County21.7 GW42
San Bernardino County19.5 GW45
Riverside County15.2 GW30
Imperial County9.5 GW37
Kings County9.5 GW15
Merced County7.3 GW18
San Joaquin County4.8 GW14
San Diego County4.3 GW23

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
CAISO148.8 GW375
LADWP16.7 GW26
IID4.5 GW33
SMUD3.6 GW15
WAPA-SN2.1 GW5

The same data set records 1,819 requests in California that were withdrawn, 429.7 GW in all. Most projects that enter a queue are never built.

Opportunity zones in California

California has 620 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 389 are newly designated and 231 carry over from the 2018 map; 106 are rural. 667 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.