California power data
As of December 31, 2025, California had 460 active interconnection requests totaling 177.9 GW of proposed generation and storage, in 40 counties. Of that, 81.9 GW (46%) has a signed interconnection agreement, and 82.0 GW proposes to be online by the end of 2028. California ranks number 2 among the states by capacity in the queue.
177.9 GW
In the queue
460
Active requests
81.9 GW
Agreement signed
82.0 GW
Proposed by 2028
What is waiting to connect in California
The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.
| Fuel | Capacity | Share |
|---|---|---|
| Battery storage | 100.1 GW | 56% |
| Solar | 64.1 GW | 36% |
| Wind | 8.1 GW | 5% |
| Other | 3.4 GW | 2% |
| Gas | 2.2 GW | 1% |
California counties with the most capacity in the queue
| County | Capacity | Requests |
|---|---|---|
| Kern County | 28.9 GW | 72 |
| Fresno County | 22.9 GW | 43 |
| Los Angeles County | 21.7 GW | 42 |
| San Bernardino County | 19.5 GW | 45 |
| Riverside County | 15.2 GW | 30 |
| Imperial County | 9.5 GW | 37 |
| Kings County | 9.5 GW | 15 |
| Merced County | 7.3 GW | 18 |
| San Joaquin County | 4.8 GW | 14 |
| San Diego County | 4.3 GW | 23 |
Who holds the queue
The grid operator or utility each request was filed with.
| Operator | Capacity | Requests |
|---|---|---|
| CAISO | 148.8 GW | 375 |
| LADWP | 16.7 GW | 26 |
| IID | 4.5 GW | 33 |
| SMUD | 3.6 GW | 15 |
| WAPA-SN | 2.1 GW | 5 |
The same data set records 1,819 requests in California that were withdrawn, 429.7 GW in all. Most projects that enter a queue are never built.
Opportunity zones in California
California has 620 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 389 are newly designated and 231 carry over from the 2018 map; 106 are rural. 667 tracts on the 2018 map are not on the new one.
Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.
Reading this for a data center site
- The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
- A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
- Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.
Sources and method
Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.