South Carolina power data

As of December 31, 2025, South Carolina had 193 active interconnection requests totaling 19.4 GW of proposed generation and storage, in 37 counties. Of that, 2.4 GW (13%) has a signed interconnection agreement, and 9.1 GW proposes to be online by the end of 2028. South Carolina ranks number 26 among the states by capacity in the queue.

19.4 GW

In the queue

193

Active requests

2.4 GW

Agreement signed

9.1 GW

Proposed by 2028

What is waiting to connect in South Carolina

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Solar8.3 GW43%
Gas8.1 GW42%
Battery storage2.2 GW11%
Other736 MW4%

South Carolina counties with the most capacity in the queue

CountyCapacityRequests
Colleton County5.7 GW19
Anderson County1.9 GW18
Williamsburg County1.2 GW14
Darlington County1.2 GW20
Berkeley County1.0 GW6
Aiken County657 MW10
Georgetown County561 MW7
Hampton County550 MW6
Marion County535 MW10
Orangeburg County452 MW6

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
S-C9.6 GW73
Duke5.7 GW85
Dominion4.1 GW35

The same data set records 475 requests in South Carolina that were withdrawn, 53.0 GW in all. Most projects that enter a queue are never built.

Opportunity zones in South Carolina

South Carolina has 113 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 61 are newly designated and 52 carry over from the 2018 map; 85 are rural. 90 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.