Wyoming power data

As of December 31, 2025, Wyoming had 73 active interconnection requests totaling 16.2 GW of proposed generation and storage, in 12 counties. Of that, 5.2 GW (32%) has a signed interconnection agreement, and 9.7 GW proposes to be online by the end of 2028. Wyoming ranks number 29 among the states by capacity in the queue.

16.2 GW

In the queue

73

Active requests

5.2 GW

Agreement signed

9.7 GW

Proposed by 2028

What is waiting to connect in Wyoming

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Wind5.7 GW35%
Solar5.5 GW34%
Gas3.1 GW19%
Other1.0 GW6%
Battery storage929 MW6%

Wyoming counties with the most capacity in the queue

CountyCapacityRequests
Laramie County4.4 GW19
Carbon County2.7 GW16
Converse County2.3 GW10
Platte County2.1 GW8
Lincoln County1.8 GW5
Sweetwater County1.2 GW2
Campbell County590 MW3
Natrona County409 MW4
Uinta County260 MW3
Goshen County200 MW1

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
PacifiCorp8.6 GW41
CLPT4.2 GW20
TSGT2.4 GW8
BHP590 MW3
PRPA350 MW1

The same data set records 268 requests in Wyoming that were withdrawn, 62.3 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Wyoming

Wyoming has 20 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 12 are newly designated and 8 carry over from the 2018 map; 16 are rural. 19 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.