New Mexico power data

As of December 31, 2025, New Mexico had 143 active interconnection requests totaling 26.9 GW of proposed generation and storage, in 20 counties. Of that, 7.3 GW (27%) has a signed interconnection agreement, and 16.8 GW proposes to be online by the end of 2028. New Mexico ranks number 20 among the states by capacity in the queue.

26.9 GW

In the queue

143

Active requests

7.3 GW

Agreement signed

16.8 GW

Proposed by 2028

What is waiting to connect in New Mexico

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Solar15.0 GW56%
Battery storage6.9 GW26%
Wind3.9 GW14%
Gas598 MW2%
Other518 MW2%

New Mexico counties with the most capacity in the queue

CountyCapacityRequests
Bernalillo County4.4 GW20
Lea County3.9 GW21
Roosevelt County3.0 GW12
Valencia County2.2 GW11
San Juan County1.8 GW8
Chaves County1.8 GW10
Santa Fe County1.6 GW9
Doña Ana County953 MW7
Luna County893 MW8
McKinley County889 MW5

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
PNM13.4 GW75
SPP9.3 GW46
EPE3.4 GW18
TSGT549 MW3
APS250 MW1

The same data set records 404 requests in New Mexico that were withdrawn, 58.1 GW in all. Most projects that enter a queue are never built.

Opportunity zones in New Mexico

New Mexico has 65 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 49 are newly designated and 16 carry over from the 2018 map; 36 are rural. 48 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.