New Mexico power data
As of December 31, 2025, New Mexico had 143 active interconnection requests totaling 26.9 GW of proposed generation and storage, in 20 counties. Of that, 7.3 GW (27%) has a signed interconnection agreement, and 16.8 GW proposes to be online by the end of 2028. New Mexico ranks number 20 among the states by capacity in the queue.
26.9 GW
In the queue
143
Active requests
7.3 GW
Agreement signed
16.8 GW
Proposed by 2028
What is waiting to connect in New Mexico
The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.
| Fuel | Capacity | Share |
|---|---|---|
| Solar | 15.0 GW | 56% |
| Battery storage | 6.9 GW | 26% |
| Wind | 3.9 GW | 14% |
| Gas | 598 MW | 2% |
| Other | 518 MW | 2% |
New Mexico counties with the most capacity in the queue
| County | Capacity | Requests |
|---|---|---|
| Bernalillo County | 4.4 GW | 20 |
| Lea County | 3.9 GW | 21 |
| Roosevelt County | 3.0 GW | 12 |
| Valencia County | 2.2 GW | 11 |
| San Juan County | 1.8 GW | 8 |
| Chaves County | 1.8 GW | 10 |
| Santa Fe County | 1.6 GW | 9 |
| Doña Ana County | 953 MW | 7 |
| Luna County | 893 MW | 8 |
| McKinley County | 889 MW | 5 |
Who holds the queue
The grid operator or utility each request was filed with.
| Operator | Capacity | Requests |
|---|---|---|
| PNM | 13.4 GW | 75 |
| SPP | 9.3 GW | 46 |
| EPE | 3.4 GW | 18 |
| TSGT | 549 MW | 3 |
| APS | 250 MW | 1 |
The same data set records 404 requests in New Mexico that were withdrawn, 58.1 GW in all. Most projects that enter a queue are never built.
Opportunity zones in New Mexico
New Mexico has 65 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 49 are newly designated and 16 carry over from the 2018 map; 36 are rural. 48 tracts on the 2018 map are not on the new one.
Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.
Reading this for a data center site
- The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
- A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
- Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.
Sources and method
Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.