Connecticut power data

As of December 31, 2025, Connecticut had 7 active interconnection requests totaling 678 MW of proposed generation and storage, in 4 counties. Of that, 648 MW (96%) has a signed interconnection agreement, and 486 MW proposes to be online by the end of 2028. Connecticut ranks number 44 among the states by capacity in the queue.

678 MW

In the queue

7

Active requests

648 MW

Agreement signed

486 MW

Proposed by 2028

What is waiting to connect in Connecticut

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Battery storage347 MW51%
Solar331 MW49%

Connecticut counties with the most capacity in the queue

CountyCapacityRequests
Hartford County281 MW4
New Haven County205 MW1
Litchfield County142 MW1
Windham County50 MW1

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
ISO-NE678 MW7

The same data set records 162 requests in Connecticut that were withdrawn, 20.5 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Connecticut

Connecticut has 61 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 24 are newly designated and 37 carry over from the 2018 map; 13 are rural. 37 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.