Tennessee power data

As of December 31, 2025, Tennessee had 53 active interconnection requests totaling 13.8 GW of proposed generation and storage, in 23 counties. Of that, 3.5 GW (25%) has a signed interconnection agreement, and 8.9 GW proposes to be online by the end of 2028. Tennessee ranks number 34 among the states by capacity in the queue.

13.8 GW

In the queue

53

Active requests

3.5 GW

Agreement signed

8.9 GW

Proposed by 2028

What is waiting to connect in Tennessee

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Gas10.7 GW77%
Solar2.1 GW15%
Battery storage747 MW5%
Other275 MW2%

Tennessee counties with the most capacity in the queue

CountyCapacityRequests
Stewart County2.4 GW2
Trousdale County2.4 GW2
Roane County1.8 GW3
Shelby County1.8 GW7
Haywood County1.2 GW3
Humphreys County950 MW3
Fayette County839 MW2
Hawkins County325 MW2
Henderson County275 MW2
Hardeman County250 MW1

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
TVA13.7 GW52
PJM100 MW1

The same data set records 243 requests in Tennessee that were withdrawn, 104.3 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Tennessee

Tennessee has 128 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 69 are newly designated and 59 carry over from the 2018 map; 72 are rural. 122 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.