Arkansas power data
As of December 31, 2025, Arkansas had 157 active interconnection requests totaling 35.4 GW of proposed generation and storage, in 42 counties. Of that, 3.7 GW (11%) has a signed interconnection agreement, and 30.3 GW proposes to be online by the end of 2028. Arkansas ranks number 14 among the states by capacity in the queue.
35.4 GW
In the queue
157
Active requests
3.7 GW
Agreement signed
30.3 GW
Proposed by 2028
What is waiting to connect in Arkansas
The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.
| Fuel | Capacity | Share |
|---|---|---|
| Solar | 28.3 GW | 80% |
| Wind | 3.0 GW | 8% |
| Battery storage | 2.0 GW | 6% |
| Gas | 1.6 GW | 5% |
| Other | 520 MW | 1% |
Arkansas counties with the most capacity in the queue
| County | Capacity | Requests |
|---|---|---|
| Mississippi County | 4.8 GW | 19 |
| Jackson County | 3.8 GW | 11 |
| Crittenden County | 2.8 GW | 11 |
| Jefferson County | 1.9 GW | 7 |
| Union County | 1.9 GW | 6 |
| Lee County | 1.6 GW | 7 |
| Lonoke County | 1.4 GW | 6 |
| St. Francis County | 1.3 GW | 5 |
| Phillips County | 1.2 GW | 7 |
| Ouachita County | 1.2 GW | 5 |
Who holds the queue
The grid operator or utility each request was filed with.
| Operator | Capacity | Requests |
|---|---|---|
| MISO | 33.3 GW | 142 |
| SPP | 2.1 GW | 15 |
The same data set records 324 requests in Arkansas that were withdrawn, 57.8 GW in all. Most projects that enter a queue are never built.
Opportunity zones in Arkansas
Arkansas has 78 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 40 are newly designated and 38 carry over from the 2018 map; 49 are rural. 55 tracts on the 2018 map are not on the new one.
Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.
Reading this for a data center site
- The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
- A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
- Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.
5 sites in Arkansas have been brought to Belisari's marketplace for powered land and data center sites.
Sources and method
Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.