Arkansas power data

As of December 31, 2025, Arkansas had 157 active interconnection requests totaling 35.4 GW of proposed generation and storage, in 42 counties. Of that, 3.7 GW (11%) has a signed interconnection agreement, and 30.3 GW proposes to be online by the end of 2028. Arkansas ranks number 14 among the states by capacity in the queue.

35.4 GW

In the queue

157

Active requests

3.7 GW

Agreement signed

30.3 GW

Proposed by 2028

What is waiting to connect in Arkansas

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Solar28.3 GW80%
Wind3.0 GW8%
Battery storage2.0 GW6%
Gas1.6 GW5%
Other520 MW1%

Arkansas counties with the most capacity in the queue

CountyCapacityRequests
Mississippi County4.8 GW19
Jackson County3.8 GW11
Crittenden County2.8 GW11
Jefferson County1.9 GW7
Union County1.9 GW6
Lee County1.6 GW7
Lonoke County1.4 GW6
St. Francis County1.3 GW5
Phillips County1.2 GW7
Ouachita County1.2 GW5

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
MISO33.3 GW142
SPP2.1 GW15

The same data set records 324 requests in Arkansas that were withdrawn, 57.8 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Arkansas

Arkansas has 78 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 40 are newly designated and 38 carry over from the 2018 map; 49 are rural. 55 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

5 sites in Arkansas have been brought to Belisari's marketplace for powered land and data center sites.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.