As of December 31, 2025, North Carolina had 179 active interconnection requests totaling 20.9 GW of proposed generation and storage, in 55 counties. Of that, 3.6 GW (17%) has a signed interconnection agreement, and 3.2 GW proposes to be online by the end of 2028. North Carolina ranks number 25 among the states by capacity in the queue.

20.9 GW

In the queue

179

Active requests

3.6 GW

Agreement signed

3.2 GW

Proposed by 2028

What is waiting to connect in North Carolina

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Gas10.2 GW49%
Battery storage4.0 GW19%
Solar3.8 GW18%
Other3.0 GW14%

North Carolina counties with the most capacity in the queue

CountyCapacityRequests
Rowan County2.6 GW4
Person County1.9 GW4
Anson County1.5 GW3
Davidson County1.5 GW2
Wayne County1.3 GW23
Stokes County1.2 GW3
Richmond County974 MW7
Robeson County946 MW9
Cleveland County905 MW4
Wake County858 MW6

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
Duke19.2 GW160
PJM1.7 GW19

The same data set records 371 requests in North Carolina that were withdrawn, 54.6 GW in all. Most projects that enter a queue are never built.

Opportunity zones in North Carolina

North Carolina has 204 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 119 are newly designated and 85 carry over from the 2018 map; 126 are rural. 180 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.