Kentucky power data
As of December 31, 2025, Kentucky had 113 active interconnection requests totaling 17.1 GW of proposed generation and storage, in 45 counties. Of that, 7.4 GW (43%) has a signed interconnection agreement, and 11.2 GW proposes to be online by the end of 2028. Kentucky ranks number 28 among the states by capacity in the queue.
17.1 GW
In the queue
113
Active requests
7.4 GW
Agreement signed
11.2 GW
Proposed by 2028
What is waiting to connect in Kentucky
The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.
| Fuel | Capacity | Share |
|---|---|---|
| Gas | 7.6 GW | 44% |
| Solar | 7.1 GW | 42% |
| Battery storage | 1.6 GW | 9% |
| Other | 543 MW | 3% |
| Wind | 200 MW | 1% |
Kentucky counties with the most capacity in the queue
| County | Capacity | Requests |
|---|---|---|
| Jefferson County | 3.2 GW | 7 |
| Trimble County | 2.0 GW | 15 |
| Todd County | 1.6 GW | 1 |
| Muhlenberg County | 1.4 GW | 6 |
| Henderson County | 1.3 GW | 6 |
| Mercer County | 922 MW | 6 |
| Fleming County | 568 MW | 6 |
| McCracken County | 526 MW | 4 |
| Webster County | 460 MW | 3 |
| Martin County | 370 MW | 4 |
Who holds the queue
The grid operator or utility each request was filed with.
| Operator | Capacity | Requests |
|---|---|---|
| LGE-KU | 6.2 GW | 32 |
| TVA | 3.9 GW | 14 |
| MISO | 3.7 GW | 24 |
| PJM | 3.3 GW | 43 |
The same data set records 319 requests in Kentucky that were withdrawn, 62.4 GW in all. Most projects that enter a queue are never built.
Opportunity zones in Kentucky
Kentucky has 137 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 84 are newly designated and 53 carry over from the 2018 map; 90 are rural. 99 tracts on the 2018 map are not on the new one.
Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.
Reading this for a data center site
- The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
- A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
- Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.
Sources and method
Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.