Kentucky power data

As of December 31, 2025, Kentucky had 113 active interconnection requests totaling 17.1 GW of proposed generation and storage, in 45 counties. Of that, 7.4 GW (43%) has a signed interconnection agreement, and 11.2 GW proposes to be online by the end of 2028. Kentucky ranks number 28 among the states by capacity in the queue.

17.1 GW

In the queue

113

Active requests

7.4 GW

Agreement signed

11.2 GW

Proposed by 2028

What is waiting to connect in Kentucky

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Gas7.6 GW44%
Solar7.1 GW42%
Battery storage1.6 GW9%
Other543 MW3%
Wind200 MW1%

Kentucky counties with the most capacity in the queue

CountyCapacityRequests
Jefferson County3.2 GW7
Trimble County2.0 GW15
Todd County1.6 GW1
Muhlenberg County1.4 GW6
Henderson County1.3 GW6
Mercer County922 MW6
Fleming County568 MW6
McCracken County526 MW4
Webster County460 MW3
Martin County370 MW4

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
LGE-KU6.2 GW32
TVA3.9 GW14
MISO3.7 GW24
PJM3.3 GW43

The same data set records 319 requests in Kentucky that were withdrawn, 62.4 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Kentucky

Kentucky has 137 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 84 are newly designated and 53 carry over from the 2018 map; 90 are rural. 99 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.