← Power data by state

Massachusetts power data

As of December 31, 2025, Massachusetts had 28 active interconnection requests totaling 5.9 GW of proposed generation and storage, in 11 counties. Of that, 2.0 GW (34%) has a signed interconnection agreement, and 5.3 GW proposes to be online by the end of 2028. Massachusetts ranks number 40 among the states by capacity in the queue.

5.9 GW

In the queue

28

Active requests

2.0 GW

Agreement signed

5.3 GW

Proposed by 2028

What is waiting to connect in Massachusetts

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Battery storage5.9 GW100%
Solar7 MW0%
Other7 MW0%
Wind5 MW0%
Gas1 MW0%

Massachusetts counties with the most capacity in the queue

CountyCapacityRequests
Middlesex County1.3 GW4
Norfolk County721 MW4
Worcester County684 MW3
Berkshire County667 MW5
Suffolk County556 MW2
Bristol County518 MW2
Barnstable County500 MW1
Hampden County465 MW3
Essex County425 MW2
Plymouth County7 MW1

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
ISO-NE5.9 GW28

The same data set records 345 requests in Massachusetts that were withdrawn, 32.3 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Massachusetts

Massachusetts has 104 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 45 are newly designated and 59 carry over from the 2018 map; 22 are rural. 81 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.