New York power data

As of December 31, 2025, New York had 187 active interconnection requests totaling 25.7 GW of proposed generation and storage, in 49 counties. Of that, 0 MW (0%) has a signed interconnection agreement, and 17.9 GW proposes to be online by the end of 2028. New York ranks number 22 among the states by capacity in the queue.

25.7 GW

In the queue

187

Active requests

0 MW

Agreement signed

17.9 GW

Proposed by 2028

What is waiting to connect in New York

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Battery storage11.1 GW43%
Solar7.3 GW28%
Wind7.3 GW28%

New York counties with the most capacity in the queue

CountyCapacityRequests
Kings County2.9 GW8
Suffolk County2.6 GW21
Franklin County1.7 GW8
Nassau County1.3 GW1
Genesee County1.2 GW6
Montgomery County1.1 GW7
Chautauqua County931 MW7
Steuben County868 MW6
Dutchess County854 MW5
Bronx County760 MW5

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
NYISO25.2 GW184
ISO-NE470 MW3

The same data set records 1,397 requests in New York that were withdrawn, 281.7 GW in all. Most projects that enter a queue are never built.

Opportunity zones in New York

New York has 430 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 213 are newly designated and 217 carry over from the 2018 map; 124 are rural. 309 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

1 site in New York has been brought to Belisari's marketplace for powered land and data center sites.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.