Vermont power data

As of December 31, 2025, Vermont had 5 active interconnection requests totaling 129 MW of proposed generation and storage, in 5 counties. Of that, 90 MW (70%) has a signed interconnection agreement, and 90 MW proposes to be online by the end of 2028. Vermont ranks number 47 among the states by capacity in the queue.

129 MW

In the queue

5

Active requests

90 MW

Agreement signed

90 MW

Proposed by 2028

What is waiting to connect in Vermont

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Solar90 MW70%
Battery storage39 MW30%

Vermont counties with the most capacity in the queue

CountyCapacityRequests
Addison County50 MW1
Bennington County20 MW1
Rutland County20 MW1
Windsor County19 MW1
Franklin County19 MW1

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
ISO-NE129 MW5

The same data set records 60 requests in Vermont that were withdrawn, 2.2 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Vermont

Vermont has 24 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 15 are newly designated and 9 carry over from the 2018 map; 24 are rural. 16 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.