Skip to content
Belisari
← Power data by state

Oklahoma power data

As of December 31, 2025, Oklahoma had 239 active interconnection requests totaling 52.5 GW of proposed generation and storage, in 57 counties. Of that, 14.4 GW (27%) has a signed interconnection agreement, and 23.9 GW proposes to be online by the end of 2028. Oklahoma ranks number 10 among the states by capacity in the queue.

52.5 GW

In the queue

239

Active requests

14.4 GW

Agreement signed

23.9 GW

Proposed by 2028

What is waiting to connect in Oklahoma

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Gas15.1 GW29%
Solar14.4 GW28%
Battery storage11.1 GW21%
Wind9.9 GW19%
Other2.0 GW4%

Oklahoma counties with the most capacity in the queue

CountyCapacityRequests
Oklahoma County5.2 GW19
Mayes County3.1 GW19
Johnston County3.1 GW10
Comanche County2.7 GW8
Payne County2.3 GW7
Texas County2.2 GW11
Creek County2.1 GW4
Pittsburg County1.8 GW5
Grady County1.7 GW8
Caddo County1.6 GW6

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
SPP50.1 GW231
AEC2.3 GW8

The same data set records 465 requests in Oklahoma that were withdrawn, 102.1 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Oklahoma

Oklahoma has 104 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 60 are newly designated and 44 carry over from the 2018 map; 57 are rural. 73 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

1 site in Oklahoma has been brought to Belisari's marketplace for powered land and data center sites.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.

Other states:TexasCaliforniaArizonaOregonIllinoisMichiganIndianaNevadaAll states