Ohio power data

As of December 31, 2025, Ohio had 163 active interconnection requests totaling 18.4 GW of proposed generation and storage, in 54 counties. Of that, 8.3 GW (45%) has a signed interconnection agreement, and 14.4 GW proposes to be online by the end of 2028. Ohio ranks number 27 among the states by capacity in the queue.

18.4 GW

In the queue

163

Active requests

8.3 GW

Agreement signed

14.4 GW

Proposed by 2028

What is waiting to connect in Ohio

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Solar12.6 GW69%
Gas3.6 GW19%
Battery storage1.5 GW8%
Wind638 MW3%
Other34 MW0%

Ohio counties with the most capacity in the queue

CountyCapacityRequests
Madison County1.7 GW9
Carroll County1.3 GW1
Trumbull County1.1 GW4
Clermont County1.1 GW3
Union County777 MW5
Wood County722 MW7
Van Wert County715 MW5
Licking County710 MW7
Highland County678 MW7
Jackson County640 MW6

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
PJM18.2 GW162
MISO135 MW1

The same data set records 589 requests in Ohio that were withdrawn, 79.6 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Ohio

Ohio has 260 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 142 are newly designated and 118 carry over from the 2018 map; 96 are rural. 196 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

4 sites in Ohio have been brought to Belisari's marketplace for powered land and data center sites.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.