Ohio power data
As of December 31, 2025, Ohio had 163 active interconnection requests totaling 18.4 GW of proposed generation and storage, in 54 counties. Of that, 8.3 GW (45%) has a signed interconnection agreement, and 14.4 GW proposes to be online by the end of 2028. Ohio ranks number 27 among the states by capacity in the queue.
18.4 GW
In the queue
163
Active requests
8.3 GW
Agreement signed
14.4 GW
Proposed by 2028
What is waiting to connect in Ohio
The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.
| Fuel | Capacity | Share |
|---|---|---|
| Solar | 12.6 GW | 69% |
| Gas | 3.6 GW | 19% |
| Battery storage | 1.5 GW | 8% |
| Wind | 638 MW | 3% |
| Other | 34 MW | 0% |
Ohio counties with the most capacity in the queue
| County | Capacity | Requests |
|---|---|---|
| Madison County | 1.7 GW | 9 |
| Carroll County | 1.3 GW | 1 |
| Trumbull County | 1.1 GW | 4 |
| Clermont County | 1.1 GW | 3 |
| Union County | 777 MW | 5 |
| Wood County | 722 MW | 7 |
| Van Wert County | 715 MW | 5 |
| Licking County | 710 MW | 7 |
| Highland County | 678 MW | 7 |
| Jackson County | 640 MW | 6 |
Who holds the queue
The grid operator or utility each request was filed with.
| Operator | Capacity | Requests |
|---|---|---|
| PJM | 18.2 GW | 162 |
| MISO | 135 MW | 1 |
The same data set records 589 requests in Ohio that were withdrawn, 79.6 GW in all. Most projects that enter a queue are never built.
Opportunity zones in Ohio
Ohio has 260 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 142 are newly designated and 118 carry over from the 2018 map; 96 are rural. 196 tracts on the 2018 map are not on the new one.
Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.
Reading this for a data center site
- The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
- A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
- Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.
4 sites in Ohio have been brought to Belisari's marketplace for powered land and data center sites.
Sources and method
Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.