West Virginia power data

As of December 31, 2025, West Virginia had 34 active interconnection requests totaling 5.2 GW of proposed generation and storage, in 20 counties. Of that, 1.3 GW (24%) has a signed interconnection agreement, and 4.3 GW proposes to be online by the end of 2028. West Virginia ranks number 42 among the states by capacity in the queue.

5.2 GW

In the queue

34

Active requests

1.3 GW

Agreement signed

4.3 GW

Proposed by 2028

What is waiting to connect in West Virginia

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Gas2.8 GW53%
Solar1.5 GW29%
Wind763 MW15%
Other101 MW2%
Battery storage30 MW1%

West Virginia counties with the most capacity in the queue

CountyCapacityRequests
Doddridge County2.1 GW1
Harrison County625 MW3
Nicholas County317 MW4
Jefferson County299 MW4
Barbour County251 MW2
Kanawha County200 MW1
Pendleton County192 MW1
Tucker County160 MW2
Hampshire County150 MW1
Grant County147 MW1

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
PJM5.2 GW34

The same data set records 145 requests in West Virginia that were withdrawn, 19.1 GW in all. Most projects that enter a queue are never built.

Opportunity zones in West Virginia

West Virginia has 52 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 29 are newly designated and 23 carry over from the 2018 map; 52 are rural. 34 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.