Georgia power data

As of December 31, 2025, Georgia had 168 active interconnection requests totaling 38.3 GW of proposed generation and storage, in 66 counties. Of that, 17.3 GW (45%) has a signed interconnection agreement, and 24.5 GW proposes to be online by the end of 2028. Georgia ranks number 12 among the states by capacity in the queue.

38.3 GW

In the queue

168

Active requests

17.3 GW

Agreement signed

24.5 GW

Proposed by 2028

What is waiting to connect in Georgia

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Solar16.3 GW43%
Gas15.6 GW41%
Battery storage5.9 GW16%
Other361 MW1%

Georgia counties with the most capacity in the queue

CountyCapacityRequests
Heard County4.2 GW7
Bartow County3.6 GW7
Coweta County2.6 GW6
Mitchell County2.4 GW6
Monroe County2.0 GW1
Hancock County2.0 GW4
Effingham County1.9 GW13
Sumter County1.4 GW5
Laurens County1.3 GW7
Jefferson County1.3 GW7

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
SOCO25.5 GW105
GTC12.8 GW63

The same data set records 509 requests in Georgia that were withdrawn, 106.5 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Georgia

Georgia has 238 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 160 are newly designated and 78 carry over from the 2018 map; 118 are rural. 196 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

3 sites in Georgia have been brought to Belisari's marketplace for powered land and data center sites.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.