Pennsylvania power data
As of December 31, 2025, Pennsylvania had 200 active interconnection requests totaling 11.4 GW of proposed generation and storage, in 52 counties. Of that, 2.3 GW (20%) has a signed interconnection agreement, and 8.5 GW proposes to be online by the end of 2028. Pennsylvania ranks number 36 among the states by capacity in the queue.
11.4 GW
In the queue
200
Active requests
2.3 GW
Agreement signed
8.5 GW
Proposed by 2028
What is waiting to connect in Pennsylvania
The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.
| Fuel | Capacity | Share |
|---|---|---|
| Solar | 8.1 GW | 71% |
| Battery storage | 1.6 GW | 14% |
| Other | 907 MW | 8% |
| Wind | 437 MW | 4% |
| Gas | 330 MW | 3% |
Pennsylvania counties with the most capacity in the queue
| County | Capacity | Requests |
|---|---|---|
| Clearfield County | 1.7 GW | 15 |
| McKean County | 953 MW | 5 |
| Dauphin County | 884 MW | 3 |
| Cambria County | 832 MW | 11 |
| Somerset County | 555 MW | 9 |
| Indiana County | 465 MW | 4 |
| Centre County | 448 MW | 14 |
| Fayette County | 439 MW | 7 |
| Elk County | 424 MW | 2 |
| Erie County | 382 MW | 6 |
Who holds the queue
The grid operator or utility each request was filed with.
| Operator | Capacity | Requests |
|---|---|---|
| PJM | 9.5 GW | 194 |
| NYISO | 1.9 GW | 6 |
The same data set records 1,347 requests in Pennsylvania that were withdrawn, 161.0 GW in all. Most projects that enter a queue are never built.
Opportunity zones in Pennsylvania
Pennsylvania has 218 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 123 are newly designated and 95 carry over from the 2018 map; 76 are rural. 204 tracts on the 2018 map are not on the new one.
Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.
Reading this for a data center site
- The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
- A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
- Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.
2 sites in Pennsylvania have been brought to Belisari's marketplace for powered land and data center sites.
Sources and method
Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.