Pennsylvania power data

As of December 31, 2025, Pennsylvania had 200 active interconnection requests totaling 11.4 GW of proposed generation and storage, in 52 counties. Of that, 2.3 GW (20%) has a signed interconnection agreement, and 8.5 GW proposes to be online by the end of 2028. Pennsylvania ranks number 36 among the states by capacity in the queue.

11.4 GW

In the queue

200

Active requests

2.3 GW

Agreement signed

8.5 GW

Proposed by 2028

What is waiting to connect in Pennsylvania

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Solar8.1 GW71%
Battery storage1.6 GW14%
Other907 MW8%
Wind437 MW4%
Gas330 MW3%

Pennsylvania counties with the most capacity in the queue

CountyCapacityRequests
Clearfield County1.7 GW15
McKean County953 MW5
Dauphin County884 MW3
Cambria County832 MW11
Somerset County555 MW9
Indiana County465 MW4
Centre County448 MW14
Fayette County439 MW7
Elk County424 MW2
Erie County382 MW6

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
PJM9.5 GW194
NYISO1.9 GW6

The same data set records 1,347 requests in Pennsylvania that were withdrawn, 161.0 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Pennsylvania

Pennsylvania has 218 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 123 are newly designated and 95 carry over from the 2018 map; 76 are rural. 204 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

2 sites in Pennsylvania have been brought to Belisari's marketplace for powered land and data center sites.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.