Missouri power data

As of December 31, 2025, Missouri had 124 active interconnection requests totaling 29.7 GW of proposed generation and storage, in 50 counties. Of that, 9.0 GW (30%) has a signed interconnection agreement, and 18.4 GW proposes to be online by the end of 2028. Missouri ranks number 17 among the states by capacity in the queue.

29.7 GW

In the queue

124

Active requests

9.0 GW

Agreement signed

18.4 GW

Proposed by 2028

What is waiting to connect in Missouri

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Solar10.2 GW34%
Gas8.3 GW28%
Battery storage5.8 GW20%
Wind3.4 GW12%
Other1.8 GW6%

Missouri counties with the most capacity in the queue

CountyCapacityRequests
Randolph County5.0 GW15
St. Charles County2.2 GW1
Jackson County2.2 GW10
Nodaway County1.4 GW4
Henry County1.3 GW4
Clay County1.2 GW6
Clinton County995 MW3
St. Louis County923 MW2
Callaway County850 MW3
Bollinger County800 MW4

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
MISO14.8 GW53
SPP8.8 GW44
AEC6.0 GW27

The same data set records 252 requests in Missouri that were withdrawn, 51.8 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Missouri

Missouri has 131 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 78 are newly designated and 53 carry over from the 2018 map; 68 are rural. 110 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

2 sites in Missouri have been brought to Belisari's marketplace for powered land and data center sites.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.