Virginia power data

As of December 31, 2025, Virginia had 271 active interconnection requests totaling 28.8 GW of proposed generation and storage, in 77 counties. Of that, 7.3 GW (25%) has a signed interconnection agreement, and 19.2 GW proposes to be online by the end of 2028. Virginia ranks number 18 among the states by capacity in the queue.

28.8 GW

In the queue

271

Active requests

7.3 GW

Agreement signed

19.2 GW

Proposed by 2028

What is waiting to connect in Virginia

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Solar13.5 GW47%
Battery storage9.9 GW34%
Gas2.7 GW9%
Wind2.7 GW9%
Other20 MW0%

Virginia counties with the most capacity in the queue

CountyCapacityRequests
Chesapeake3.0 GW7
Sussex County1.8 GW8
Fluvanna County1.7 GW3
Chesterfield County1.6 GW10
Brunswick County1.6 GW10
Pittsylvania County1.3 GW11
Halifax County1.1 GW10
Charlotte County975 MW8
Lunenburg County766 MW7
Loudoun County715 MW5

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
PJM28.8 GW271

The same data set records 861 requests in Virginia that were withdrawn, 85.1 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Virginia

Virginia has 153 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 81 are newly designated and 72 carry over from the 2018 map; 77 are rural. 146 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.