Florida power data

As of December 31, 2025, Florida had 230 active interconnection requests totaling 22.9 GW of proposed generation and storage, in 42 counties. Of that, 2.9 GW (13%) has a signed interconnection agreement, and 12.5 GW proposes to be online by the end of 2028. Florida ranks number 24 among the states by capacity in the queue.

22.9 GW

In the queue

230

Active requests

2.9 GW

Agreement signed

12.5 GW

Proposed by 2028

What is waiting to connect in Florida

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Solar15.0 GW66%
Gas3.5 GW15%
Other2.7 GW12%
Battery storage1.8 GW8%

Florida counties with the most capacity in the queue

CountyCapacityRequests
Hendry County3.0 GW40
Miami-Dade County2.7 GW3
Osceola County2.0 GW9
St. Lucie County1.8 GW24
DeSoto County1.2 GW16
Collier County1.1 GW15
Charlotte County1.0 GW14
Martin County1.0 GW14
Duval County995 MW6
Pasco County862 MW4

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
FPL15.1 GW164
Duke5.1 GW44
OUC1.1 GW6
JEA995 MW6
TEC624 MW10

The same data set records 451 requests in Florida that were withdrawn, 72.0 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Florida

Florida has 342 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 218 are newly designated and 124 carry over from the 2018 map; 98 are rural. 314 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.