Nebraska power data

As of December 31, 2025, Nebraska had 80 active interconnection requests totaling 15.8 GW of proposed generation and storage, in 31 counties. Of that, 5.4 GW (34%) has a signed interconnection agreement, and 7.1 GW proposes to be online by the end of 2028. Nebraska ranks number 31 among the states by capacity in the queue.

15.8 GW

In the queue

80

Active requests

5.4 GW

Agreement signed

7.1 GW

Proposed by 2028

What is waiting to connect in Nebraska

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Gas5.6 GW35%
Solar5.5 GW35%
Wind2.3 GW14%
Battery storage2.0 GW12%
Other522 MW3%

Nebraska counties with the most capacity in the queue

CountyCapacityRequests
Lancaster County3.8 GW20
Cass County2.6 GW10
Gage County1.5 GW6
Burt County1.1 GW4
Nemaha County724 MW3
Douglas County712 MW5
Custer County500 MW2
Pierce County423 MW2
Wayne County385 MW2
Dakota County360 MW2

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
SPP15.2 GW78
BHP550 MW2

The same data set records 250 requests in Nebraska that were withdrawn, 45.1 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Nebraska

Nebraska has 28 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 15 are newly designated and 13 carry over from the 2018 map; 12 are rural. 31 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.