Montana power data

As of December 31, 2025, Montana had 45 active interconnection requests totaling 11.3 GW of proposed generation and storage, in 16 counties. Of that, 1.2 GW (11%) has a signed interconnection agreement, and 9.6 GW proposes to be online by the end of 2028. Montana ranks number 37 among the states by capacity in the queue.

11.3 GW

In the queue

45

Active requests

1.2 GW

Agreement signed

9.6 GW

Proposed by 2028

What is waiting to connect in Montana

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Wind7.6 GW67%
Solar2.4 GW21%
Other738 MW7%
Gas487 MW4%
Battery storage100 MW1%

Montana counties with the most capacity in the queue

CountyCapacityRequests
Wheatland County3.2 GW8
Rosebud County2.9 GW5
Meagher County1.5 GW4
Yellowstone County1.2 GW6
Lincoln County646 MW1
Stillwater County595 MW4
Wibaux County335 MW3
Big Horn County308 MW2
Custer County225 MW1
Broadwater County160 MW2

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
NWMT7.1 GW30
PacifiCorp2.0 GW5
Avista900 MW2
BPA648 MW3
SPP534 MW4

The same data set records 395 requests in Montana that were withdrawn, 33.5 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Montana

Montana has 25 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 15 are newly designated and 10 carry over from the 2018 map; 15 are rural. 17 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

1 site in Montana has been brought to Belisari's marketplace for powered land and data center sites.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.