Idaho power data

As of December 31, 2025, Idaho had 64 active interconnection requests totaling 12.2 GW of proposed generation and storage, in 21 counties. Of that, 4.1 GW (33%) has a signed interconnection agreement, and 7.9 GW proposes to be online by the end of 2028. Idaho ranks number 35 among the states by capacity in the queue.

12.2 GW

In the queue

64

Active requests

4.1 GW

Agreement signed

7.9 GW

Proposed by 2028

What is waiting to connect in Idaho

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Solar5.9 GW48%
Battery storage2.4 GW19%
Gas1.9 GW15%
Wind1.7 GW14%
Other398 MW3%

Idaho counties with the most capacity in the queue

CountyCapacityRequests
Elmore County2.5 GW10
Ada County2.0 GW11
Bingham County1.8 GW8
Power County1.6 GW4
Owyhee County993 MW5
Canyon County594 MW4
Benewah County500 MW2
Jerome County320 MW2
Bannock County301 MW2
Clearwater County300 MW1

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
IP7.8 GW42
PacifiCorp3.1 GW13
BPA902 MW3
Avista455 MW6

The same data set records 556 requests in Idaho that were withdrawn, 89.2 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Idaho

Idaho has 25 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 20 are newly designated and 5 carry over from the 2018 map; 9 are rural. 23 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.