Mississippi power data

As of December 31, 2025, Mississippi had 88 active interconnection requests totaling 16.1 GW of proposed generation and storage, in 39 counties. Of that, 2.9 GW (18%) has a signed interconnection agreement, and 13.6 GW proposes to be online by the end of 2028. Mississippi ranks number 30 among the states by capacity in the queue.

16.1 GW

In the queue

88

Active requests

2.9 GW

Agreement signed

13.6 GW

Proposed by 2028

What is waiting to connect in Mississippi

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Solar9.9 GW61%
Gas3.3 GW21%
Battery storage1.9 GW12%
Wind947 MW6%

Mississippi counties with the most capacity in the queue

CountyCapacityRequests
DeSoto County1.9 GW6
Sunflower County1.7 GW11
Hinds County1.4 GW3
Madison County877 MW6
Clay County850 MW5
Warren County820 MW1
Lowndes County820 MW2
Jasper County715 MW4
Tunica County697 MW4
Washington County670 MW3

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
MISO12.8 GW65
TVA2.8 GW18
SOCO490 MW5

The same data set records 314 requests in Mississippi that were withdrawn, 85.5 GW in all. Most projects that enter a queue are never built.

Opportunity zones in Mississippi

Mississippi has 102 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 46 are newly designated and 56 carry over from the 2018 map; 78 are rural. 55 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.