New Jersey power data

As of December 31, 2025, New Jersey had 65 active interconnection requests totaling 14.5 GW of proposed generation and storage, in 19 counties. Of that, 1.2 GW (8%) has a signed interconnection agreement, and 4.2 GW proposes to be online by the end of 2028. New Jersey ranks number 32 among the states by capacity in the queue.

14.5 GW

In the queue

65

Active requests

1.2 GW

Agreement signed

4.2 GW

Proposed by 2028

What is waiting to connect in New Jersey

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Wind9.5 GW65%
Battery storage3.7 GW25%
Solar706 MW5%
Gas410 MW3%
Other257 MW2%

New Jersey counties with the most capacity in the queue

CountyCapacityRequests
Monmouth County5.3 GW7
Atlantic County2.7 GW6
Middlesex County2.6 GW2
Salem County854 MW5
Camden County600 MW2
Warren County436 MW11
Hudson County350 MW2
Gloucester County321 MW5
Union County308 MW2
Hunterdon County300 MW2

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
PJM14.5 GW65

The same data set records 882 requests in New Jersey that were withdrawn, 92.2 GW in all. Most projects that enter a queue are never built.

Opportunity zones in New Jersey

New Jersey has 130 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 60 are newly designated and 70 carry over from the 2018 map; 13 are rural. 102 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.