South Dakota power data

As of December 31, 2025, South Dakota had 47 active interconnection requests totaling 9.4 GW of proposed generation and storage, in 21 counties. Of that, 3.4 GW (37%) has a signed interconnection agreement, and 5.7 GW proposes to be online by the end of 2028. South Dakota ranks number 38 among the states by capacity in the queue.

9.4 GW

In the queue

47

Active requests

3.4 GW

Agreement signed

5.7 GW

Proposed by 2028

What is waiting to connect in South Dakota

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. A project that pairs solar with a battery is split between the two.

FuelCapacityShare
Wind3.2 GW34%
Solar2.2 GW23%
Gas1.7 GW18%
Other1.6 GW18%
Battery storage700 MW7%

South Dakota counties with the most capacity in the queue

CountyCapacityRequests
Campbell County2.1 GW10
Deuel County1.5 GW3
Brookings County1.2 GW3
Brown County512 MW4
Grant County500 MW2
Clark County450 MW2
Codington County440 MW3
Meade County400 MW4
McPherson County400 MW2
Day County300 MW1

Who holds the queue

The grid operator or utility each request was filed with.

OperatorCapacityRequests
MISO4.8 GW18
BHP2.3 GW13
SPP1.6 GW9
WAPA-IS602 MW4
NWMT8 MW3

The same data set records 247 requests in South Dakota that were withdrawn, 60.0 GW in all. Most projects that enter a queue are never built.

Opportunity zones in South Dakota

South Dakota has 25 opportunity zones on the map certified on November 5, 2026, which takes effect January 1, 2027. 7 are newly designated and 18 carry over from the 2018 map; 18 are rural. 9 tracts on the 2018 map are not on the new one.

Newly designated and carried over are Belisari's comparison of the two maps, tract by tract.

Reading this for a data center site

  • The queue is the supply side: generation and storage asking to connect. It does not show data center or other load requests, which utilities and grid operators do not publish by location.
  • A county with a large queue has developers competing for the same substations and lines. That can mean new supply nearby, and it can also mean a crowded study process.
  • Capacity with a signed agreement is the likelier to be built. Capacity still in study is a claim on the grid, not a plant.

1 site in South Dakota has been brought to Belisari's marketplace for powered land and data center sites.

Sources and method

Interconnection queue: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (CC BY 4.0), requests through December 31, 2025. Projects are placed by the county they name; about 1% name none and are left out. “Agreement signed” means the request has an executed interconnection agreement or is in construction. Opportunity zones: U.S. Treasury, CDFI Fund: Opportunity Zones. Counts and breakdowns are Belisari's, from the files behind its power map. Not investment or tax advice.