Powered land, powered shell, turnkey: the five stages a site is sold at
A data center site can change hands at five points, from land with approved power to a running facility. What is included at each, and who tends to buy there.
Belisari · November 16, 2026 · 4 min read
The same site is worth different things, to different buyers, depending on how far it has been taken. There are five points at which a data center site commonly changes hands. Each one moves work, cost and risk from the buyer to the seller, and the price per megawatt rises with it.
1. Powered land
Land under control, with power approved by the utility and zoning or use confirmed. Nothing is built yet. What changes hands is the land, the right to the power and the right to build. It is the lowest price per megawatt and leaves the buyer the most work and the most freedom over design. Owner-users and data center developers tend to buy here.
2. Energy infrastructure built
The land with the infrastructure that takes the power: the utility's facilities, the substation, protection and commissioning. It may not be energized yet. The buyer skips the longest and least predictable part of the schedule.
3. Powered shell
A building, designed and permitted, with utility power delivered to it and nothing inside. There is no electrical distribution or cooling yet; the tenant fits it out to its own design.
4. Fitted data center
Often called turnkey. The inside is built out and commissioned: switchgear, UPS and backup power, power to the racks, and cooling. It is ready for servers. This is the fastest way to capacity and the highest price per megawatt of the built stages.
5. Operating facility
A running data center with its compute installed. What is sold is a business, with its customers and contracts, and diligence turns from construction risk to operations.
How to choose a stage
- A seller who sells early needs the least capital and exits fastest, at the lowest price per megawatt.
- A buyer who buys early pays least and controls the design, and carries the build and the utility's schedule.
- The later the stage, the more the site has been designed for someone. That narrows the pool of buyers it fits.
- At every stage, the first thing to read is the utility paper: what is approved, for whom, and whether it transfers.
Belisari's advisory page sets out each stage in full: what the seller delivers, what the buyer takes on, who tends to buy, and which contract structures fit.