What the interconnection queue tells a site buyer, and what it does not

At the end of 2025, 1,845 GW of generation and storage was waiting to connect to the U.S. grid. How to read that for a data center site.

Belisari · November 16, 2026 · 4 min read

The interconnection queue is the list of power plants and batteries that have asked to connect to the grid. Lawrence Berkeley National Laboratory gathers the queues of grid operators and utilities across the country each year. In its 2026 edition, covering requests through December 31, 2025, the active requests that name a county come to 8,413 projects and 1,845 GW.

What is in it

Solar and battery storage make up most of the capacity: about 767 GW of solar and 552 GW of storage, against 252 GW of gas and 209 GW of wind. Texas has the most by far, at 438 GW, followed by California, Arizona, Oregon and Illinois.

Most of it will not be built

A queue is a list of requests, not of plants. About 445 GW of the active capacity, roughly a quarter, has a signed interconnection agreement or is in construction. The same data set records 22,833 requests that were withdrawn. Capacity with a signed agreement is the best public sign of what will actually arrive.

What it tells a site buyer

  • Where new supply is proposed. A county with signed projects nearby may have more generation and more transmission work coming.
  • Where the grid is crowded. Many requests at the same substations and lines mean longer studies for everyone, loads included.
  • Who is active. The queue names the utility or grid operator holding each request, and often the point of interconnection.

What it does not tell you

  • It is the supply side only. Data center and other load requests are not published by location.
  • It says nothing about whether a particular site can be served. That takes a load study by the utility.
  • It is a snapshot. A new edition comes out each spring, and queues change in between.

Belisari publishes the queue by state and county, with the fuel mix and the share with signed agreements, at belisari.com/data, and draws it on its power map.

Work with Belisari

Bring us a site, a load, or a thesis.

Landowners, operators, utilities, and investors — tell us what you're working on and we'll tell you what the power is really worth and what it takes to transact.