Project Goldfinger

Texas · ERCOT

Capacity
10–30 MW
Power
12.47 kVDistribution
Stage
Fitted data center
Energization
Energized
Land
1 acLeased · water · fiber

Where it is, its land and its data room follow under NDA.

View All Site Details

Power*

10–30

Total MW

5–15

Energized MW

5–15

Authorized MW

Tranches

Grid 10–30 MW

  • 5–15 MWDistribution · 12.47 kVLoad approvedQ4 2026
  • 5–15 MWDistribution · 12.47 kVEnergizedLive

* Before an NDA, capacity and each tranche are shown as rounded ranges and timing by quarter. Exact megawatts, tranche sizes and capacity approvals follow under NDA.

Land

1ac

Acres, about

Leased

Land control

  • WaterOn site
  • FiberOn site
  • GasNot stated

TexasPre-NDA · state only

The parcel, softened, is in the teaser. Where it is and its true outline follow under NDA.

Development stage

  1. Powered land
  2. Energy Build
  3. Powered shell
  4. Fitted data centerReached
  5. OperatingIn progress

Fitted data center: The inside built out and commissioned: switchgear, backup, power to the racks and cooling. Ready for servers.

Deal structure

On request

Development framework

Power & grid approvalCompletedEntitlements & permittingCompletedLand & site controlCompletedInfrastructureCompletedEnergizationCompletedDesignCompletedShellCompletedFit-outCompletedComputeCompletedOperationalNot startedPOWER TO THE SITEDATA CENTER BUILD

Gold is completed, amber in progress.

Permits

Permitting detail opens under NDA.

* Before an NDA, capacity and each tranche are shown as rounded ranges and timing by quarter. Exact megawatts, tranche sizes and capacity approvals follow under NDA. Shared in confidence for evaluation. Numbers as reported by the owner; subject to diligence.