Project Avi

Texas · ERCOT

Capacity
300–1,200 MW
Power
345 kVTransmission
Stage
Powered land in progress
Energization
Q4 2028
Land
470 acUnder PSA · water

Where it is, its land and its data room follow under NDA.

View All Site Details

Power*

1,100–1,200

Total MW

250–350

In study MW

800–900

Potential MW

Tranches

Grid 1,100–1,200 MW

  • 800–900 MWTransmissionNot startedNo date yet
  • 250–350 MWTransmission · 345 kVLoad approval pendingQ4 2028

* Before an NDA, capacity and each tranche are shown as rounded ranges and timing by quarter. Exact megawatts, tranche sizes and capacity approvals follow under NDA.

Land

470ac

Acres, about

Under PSA

Land control

  • WaterOn site
  • FiberNot stated
  • GasNot stated

TexasPre-NDA · state only

The parcel, softened, is in the teaser. Where it is and its true outline follow under NDA.

Development stage

  1. Powered landIn progress
  2. Energy BuildAfter handoff
  3. Powered shellAfter handoff
  4. Fitted data centerAfter handoff
  5. OperatingAfter handoff

Powered land in progress: land under control, power approved, and zoning or use confirmed.

Deal structure

Powered landEntity sale, JV

Development framework

Power & grid approvalIn progressEntitlements & permittingNot startedLand & site controlCompletedInfrastructureAfter handoffEnergizationAfter handoffDesignAfter handoffShellAfter handoffFit-outAfter handoffComputeAfter handoffOperationalAfter handoffPOWER TO THE SITEDATA CENTER BUILD

Gold is completed, amber in progress. What lies past the flag is dashed: the buyer's to build after the handoff.

Permits

Permitting detail opens under NDA.

* Before an NDA, capacity and each tranche are shown as rounded ranges and timing by quarter. Exact megawatts, tranche sizes and capacity approvals follow under NDA. Shared in confidence for evaluation. Numbers as reported by the owner; subject to diligence.