Project Aurum

South Dakota · WEIM

Capacity
10–50 MW
Power
69 kVTransmission
Stage
Powered land in progress
Energization
Q2 2027
Land
16 acUnder PSA

Where it is, its land and its data room follow under NDA.

View All Site Details

Power*

50–70

Total MW

50–70

In study MW

Tranches

Grid 50–70 MW

  • 30–50 MWTransmission · 69 kVLoad approval pendingQ4 2027
  • 10–20 MWDistribution · 12.47 kVLoad approval pendingQ2 2027

* Before an NDA, capacity and each tranche are shown as rounded ranges and timing by quarter. Exact megawatts, tranche sizes and capacity approvals follow under NDA.

Land

16ac

Acres, about

Under PSA

Land control

  • WaterNot stated
  • FiberNot stated
  • GasNot stated

South DakotaPre-NDA · state only

The parcel, softened, is in the teaser. Where it is and its true outline follow under NDA.

Development stage

  1. Powered landIn progress
  2. Energy BuildAfter handoff
  3. Powered shellAfter handoff
  4. Fitted data centerAfter handoff
  5. OperatingAfter handoff

Powered land in progress: land under control, power approved, and zoning or use confirmed.

Deal structure

Powered landEntity sale, JV

Development framework

Power & grid approvalIn progressEntitlements & permittingIn progressLand & site controlCompletedInfrastructureAfter handoffEnergizationAfter handoffDesignAfter handoffShellAfter handoffFit-outAfter handoffComputeAfter handoffOperationalAfter handoffPOWER TO THE SITEDATA CENTER BUILD

Gold is completed, amber in progress. What lies past the flag is dashed: the buyer's to build after the handoff.

Permits

Permitting detail opens under NDA.

* Before an NDA, capacity and each tranche are shown as rounded ranges and timing by quarter. Exact megawatts, tranche sizes and capacity approvals follow under NDA. Shared in confidence for evaluation. Numbers as reported by the owner; subject to diligence.