Project Aurum
South Dakota · WEIM
- Capacity
- 10–50 MW
- Power
- 69 kVTransmission
- Stage
- Powered land in progress
- Energization
- Q2 2027
- Land
- 16 acUnder PSA
Where it is, its land and its data room follow under NDA.
View All Site DetailsPower*
50–70
Total MW
50–70
In study MW
Tranches
Grid 50–70 MW
- 30–50 MWTransmission · 69 kVLoad approval pendingQ4 2027
- 10–20 MWDistribution · 12.47 kVLoad approval pendingQ2 2027
* Before an NDA, capacity and each tranche are shown as rounded ranges and timing by quarter. Exact megawatts, tranche sizes and capacity approvals follow under NDA.
Land
16ac
Acres, about
Under PSA
Land control
- WaterNot stated
- FiberNot stated
- GasNot stated
South DakotaPre-NDA · state only
The parcel, softened, is in the teaser. Where it is and its true outline follow under NDA.
Development stage
- Powered landIn progress
- Energy BuildAfter handoff
- Powered shellAfter handoff
- Fitted data centerAfter handoff
- OperatingAfter handoff
Powered land in progress: land under control, power approved, and zoning or use confirmed.
Deal structure
Powered landEntity sale, JV
Development framework
Gold is completed, amber in progress. What lies past the flag is dashed: the buyer's to build after the handoff.
Permits
Permitting detail opens under NDA.
* Before an NDA, capacity and each tranche are shown as rounded ranges and timing by quarter. Exact megawatts, tranche sizes and capacity approvals follow under NDA. Shared in confidence for evaluation. Numbers as reported by the owner; subject to diligence.